Hey #TeamShadow,
Last week we added a new section beneath each data center, “Start of week”. This marks the starting point of activations for each datacenter in a given week. Combine this with our target for your datacenter and you should be able to determine whether you’ll be activated this week!
For New York pre-orders, some users who pre-ordered between May 27th and July 16th and were promised activation in July 2020 will have their Shadow delivery delayed. As there is still next week to process activations in July and activations are processed on a first-come first-served basis, we will email all impacted users that will be delayed by the end of July with their adjusted delivery timeline.
Given the feedback from previous weekly activation updates, we’d like to clearly address that we’re monitoring Chicago and Texas closely to avoid any delays similar to New York. We will update this thread with any developments during the week if we have any, and of course provide you the situation in next Monday’s update. Please keep the feedback coming, and thank you for your patience despite the wait for activation.
Santa Clara, Paris, and Amsterdam continue to activate at a fairly regular pace each.
As a reminder:
-We activate Monday through Thursday
-Beginning at 8am local time each day for each datacenter
Below is the activation information by datacenter. You can check which datacenter you belong to here.
CHICAGO:
If pre-order date is before May 26th:
Activation this week
If pre-order date is between May 26th - July 16th
Activations starting from July 2020 (after pre-orders before May 26th)
If pre-order date is July 16th or later:
Activation in August 2020
Start of week:
May 20th pre-order date
Target by next Monday:
Latest activation has May 28th pre-order date
TEXAS:
If pre-order date is between May 26th - June 1st:
Activation this week
If pre-order date is June 1st or later:
Activations starting from July 2020 (after pre-orders before June 1st)
Start of week:
May 29th pre-order date
Target by next Monday:
Latest activation has June 4th pre-order date
NEW YORK:
If pre-order date is before May 26th:
Activation this week
If pre-order date is May 26th or later:
Activations starting from July 2020 (after pre-orders before May 26th)
If pre-order date is July 16th or later:
Activation in September 2020
Start of week:
May 21st pre-order date
Target by next Monday:
Latest activation has May 27th pre-order date
SANTA CLARA:
If pre-order date is is before July 16th:
Activation in July 2020
If pre-order date is July 16th or later:
Activation in August 2020 (hopeful to activate early)
Start of week:
July 7th pre-order date
Target by next Monday:
Latest activation has July 16th pre-order date
PARIS:
If pre-order date is before June 10th:
Pre-orders are on track to be delivered late summer (August-September)
If pre-order date is June 10th or later:
Activations starting October 2020
Start of week:
April 19th pre-order date
Target by next Monday:
Latest activation has April 25th pre-order date
AMSTERDAM:
If pre-order date is before June 10th:
Activations starting July 2020
If pre-order date is June 10th or later:
Activations starting July 2020
Start of week:
May 27th pre-order date
Target by next Monday:
Latest activation has June 2nd pre-order date